ALTA Survey: What It Covers and How to Order One for a Land Deal

What a 2026 ALTA/NSPS Land Title Survey includes, which Table A items to order for a land deal, what to send the surveyor, and how to read the plat before closing.

For developers, land buyers, acquisition and feasibility teams, and their counsel ordering or reviewing an ALTA survey before closing on a parcel.

By Site Diligence Desk Editors · Updated

What an ALTA survey is

An ALTA survey, formally an ALTA/NSPS Land Title Survey, is a boundary survey done to a national standard set jointly by the American Land Title Association (ALTA) and the National Society of Professional Surveyors (NSPS). That standard, the Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys, exists so a title insurer can insure a property without a blanket exception for matters that only a survey and an inspection of the ground would reveal.

The current version is the 2026 standard, effective February 23, 2026. As of that date it superseded every earlier version, including the 2021 standard. The standard says the request must specify that a "2026 ALTA/NSPS Land Title Survey" is required and which optional Table A items to include, so write both into the engagement.

Under the standard, a complete ALTA/NSPS Land Title Survey has four parts:

  1. Fieldwork. Monuments, boundary lines, access, lines of possession, buildings, easement evidence, utilities, cemeteries and water features, located on the ground (Section 5).
  2. The plat or map. The fieldwork drawn against the title documents the surveyor was given, with the record description, dimensions, easements, notes and a summary of the title commitment's survey-related exceptions (Section 6).
  3. Table A items. Any of the optional items the client ordered, such as flood zone, topography, zoning setbacks or an encroachment table.
  4. Certification. The surveyor's signed statement, to the parties named, that the survey meets the 2026 standard and includes the listed Table A items (Section 7).

State law still governs. Where a state's survey statutes, rules or standards of practice conflict with the ALTA/NSPS standard, the more stringent applies, so the same survey can look a little different from state to state.

Why buyers and lenders ask for one

Public records do not show everything that affects title. A neighbour's fence over the line, a driveway that crosses the parcel, an unrecorded utility line or a building over a setback only shows up on the ground. An ALTA survey ties what the surveyor finds on the ground to the documents in the title commitment, so the insurer, the lender and the buyer all work from the same picture.

Commercial lenders commonly make an ALTA survey a loan condition, often with a list of required Table A items and parties to certify to. Title companies usually rely on it to remove or narrow the survey exception in the policy and to issue survey-based endorsements; which endorsements are available varies by state. Ask your lender and title company for their survey requirements in writing before you engage a surveyor, so the scope is set once.

Boundary survey
Establishes or retraces the property lines and corners under state standards. It may not tie every recorded easement to the ground or follow a uniform national format.
ALTA/NSPS Land Title Survey
A boundary survey plus the national requirements: review of the title commitment and recorded easements, a summary of every survey-related exception, set fieldwork and plat contents, optional Table A items, and a standard certification to named parties.
Topographic or engineering design survey
Maps ground elevations, utilities and features in the detail civil design needs. The standard says that if you want an engineering design survey as part of the ALTA survey, negotiate it as a Table A item 21, beyond items 5 and 11.

What to send the surveyor

The surveyor can only tie title matters to the ground if they have the title matters. Section 4 of the standard says the surveyor must be provided with:

  • A complete copy of the most recent title commitment, or other title evidence satisfactory to the insurer.
  • The current record description of the property, or of the parent parcel for a property not yet separately described.
  • Copies of recorded easements that benefit the property, and recorded easements, servitudes and covenants that burden it.
  • Any unrecorded documents you want the survey to reference, such as a draft easement or a lease.

Order the title commitment first, with copies of every exception document, and send the whole package to the surveyor. If documents are missing, the surveyor does only the research the state requires and the contract covers, and the summary of exceptions will be thin.

Tell the surveyor in writing what you plan to build. The standard has features located and dimensions shown to the precision the surveyor judges appropriate for the planned use, when the client, lender or insurer reports it in writing; otherwise to the existing use. A survey scoped for a vacant field reads differently from one scoped for a multifamily project. Arrange permission for the surveyor to enter the property and, where needed, adjoining land and offsite easements.

What every ALTA survey must show

These are required whether or not you order any Table A items:

Boundary and precision
Boundary lines and corners set under boundary law principles, the monuments found (and set, where Table A item 1 or the state requires it), and the dimensions needed to close the boundary. Relative positional precision between adjacent corners may not exceed 2 cm (0.07 ft) plus 50 parts per million, or the plat must note why.
Record versus measured
The record description and all its distances and directions, with measured dimensions shown alongside where they differ significantly. Any new description must say whether it describes the same land as the record description, and if not, how it differs.
Gaps and overlaps
How the boundaries relate to the adjoining properties and, for a site made of several parcels, any gaps or overlaps between them, disclosed to the insurer and client.
Access
Abutting streets and their travelled ways, observed physical access such as curb cuts and driveways, and a note if no physical access to an abutting street was observed. Rights-of-way widths and their source.
Possession and improvements
Evidence of possession along the perimeter, walls, buildings and fences within five feet of each side of the boundary, and potentially encroaching structures, with no legal opinion on ownership. A note where access within five feet of the line was restricted.
Easements
Every plottable easement in the documents, plus observed evidence of uses not in the documents, such as paths, drives, ditches and utility lines, which can point to prescriptive rights.
Utilities, cemeteries and water
Surface evidence of utilities on and near the property, cemeteries and gravesites disclosed or observed, and springs, ponds, streams, ditches and marshes on or within five feet of the boundary.
Presentation
A plat at a standard engineering scale with a north arrow, legend, vicinity map, the caption "ALTA/NSPS Land Title Survey", the surveyor's seal and contact details, and the note "No buildings observed" on vacant land.

Which Table A items to order for a land deal

Table A lists 20 optional items, plus item 21 for anything else you negotiate. The exact wording and the fee of each item can be negotiated, and any change must be explained on the plat. For raw or lightly improved land bought for development, these are the items that usually earn their place:

1. Monuments
Monuments set at the major corners not already marked. Useful for later staking and for showing the lines to engineers and neighbours.
3. Flood zone
The flood zone classification from the Flood Insurance Rate Map, by scaled map location and graphic plotting only. It is not an elevation certificate or a map amendment. See Reading FEMA FIRM Panels for Development Projects.
4. Gross land area
The parcel's area, and other areas you specify. Purchase price, density and lot coverage are often calculated from it, so ask for any net areas you need, such as area outside rights-of-way.
5. Vertical relief
Contours or spot elevations with their source, interval and datum. Enough for a test fit and early grading questions; for civil design, negotiate a design survey under item 21.
6(a) and 6(b). Zoning
Zoning classification, setbacks, height, floor area and parking listed on the plat, and setbacks drawn on it, but only from a zoning report or letter you provide, and for 6(b) only where the setbacks need no interpretation by the surveyor. See Setback and Buildable Envelope Diagrams for Infill Sites.
11(a) and 11(b). Underground utilities
Underground utilities from plans you provide and from a private utility locate, combined with the surface evidence. The standard warns that without excavation their location cannot be shown accurately, completely and reliably.
13 and 14. Adjoiners and nearest street
Names of adjoining owners from current tax records, and the distance to the nearest intersecting street.
16 and 17. Recent work and road changes
Evidence of recent earth moving or construction, and proposed changes to street right-of-way lines where the controlling jurisdiction makes them available. A road widening can take frontage you were counting on.
18. Offsite easements
Plottable easements that benefit the property, such as an access or utility easement over a neighbour's land. Essential for a landlocked or flag parcel.
19. Professional liability insurance
A minimum amount of surveyor's professional liability insurance in force for the contract term; your lender may set the amount.
20. Encroachment table
A table of potential encroachments over boundary lines, into documented easements and rights-of-way, into setbacks (where you gave the setbacks under item 6 or they are recorded), and access or use across neighbouring land without an easement.

Items 7, 9 and 10 (building dimensions and height, parking counts, party walls) matter for improved property; leave them off a vacant parcel. Item 15 lets the surveyor show features away from the boundary from imagery rather than field location, only with written agreement on the source and a note on the plat. Item 21 is where anything else goes, such as locating flagged wetland delineation lines from your consultant's report or extra areas your lender wants.

The certification

The plat must carry the standard's certification without alteration, except where state law requires otherwise. It is addressed to the insured, the lender, the title insurer and anyone else negotiated with the client, states that the survey was made under the 2026 standard, lists the Table A items included, and gives the date fieldwork was completed and the date of the plat. On request it can be extended to the lender's successors and assigns.

  • Check the names against the title commitment and the loan documents. Certify to the entity that will actually take title, not a parent company or a placeholder.
  • Check the Table A items listed match the items you ordered and your lender requires.
  • Check the year in the certification. A survey certified to the 2021 standard is not a 2026 survey; ask your lender and title company whether an update is needed.

How to read the plat

Review the draft with counsel and the title company before it is finalized; corrections are cheaper then. Work through it in this order:

  1. The title source note. The plat names the title commitment used, its effective date and the insurer. Confirm it is the current commitment; if the commitment has been updated with new exceptions, the survey needs to catch up.
  2. The summary of exceptions. Every right-of-way, easement and survey-related matter from the commitment is listed with its record information, whether it lies within or crosses the property, and a note where it applies: location shown, location cannot be determined, no evidence observed, blanket easement, does not affect the property, limits access to an abutting road, illegible, or possibly released.
  3. Blanket and undeterminable easements. An easement with no defined location can sit anywhere on the site. Ask counsel whether it can be released, relocated or confined to a defined strip before closing.
  4. Encroachments and possession. Read the item 20 table if ordered, then the fences, drives, structures and paths along the lines. Each is a question for title: an exception, an endorsement, a boundary agreement or an easement.
  5. Access. Confirm that physical access was observed to the road you plan to use and that the property abuts it, or that a recorded easement reaches it. A note that no physical access was observed is a red flag for a development site.
  6. Surveyor's notes. Read every note: differences between record and measured dimensions, new descriptions, gaps and overlaps, restricted access along the lines, precision not met, unexpected recorded easements the surveyor advised the insurer about, and statements made by owners or occupants about the boundary.

Then send the final plat to the title company, which will compare it to the commitment and say which survey exceptions it will remove, modify or keep, and which endorsements it will issue.

What an ALTA survey does not tell you

The standard sets no age limit on a survey. How recent a survey must be, and whether an older one can be updated and recertified rather than redone, is up to your title insurer and lender; ask them early, especially if you are buying from a seller with an existing survey.

Where it fits in site feasibility

Order the ALTA survey as soon as the title commitment arrives, so title objections drawn from the survey fall inside your contract's objection period. Then use it as the base for the rest of the feasibility work:

Fees and turnaround depend on the parcel's size, terrain, vegetation and records, the Table A items ordered and the surveyor's backlog. Get written quotes from more than one licensed surveyor in the property's state, quoted against the same Table A list, and confirm the delivery date against your contract dates before you sign.

ALTA survey checklist for a land deal

  • Get your lender's and title company's survey requirements in writing: Table A items, certification parties, insurance amount, how recent.
  • Order the title commitment with copies of every exception document, and send it all to the surveyor.
  • Engage a surveyor licensed in the property's state for a "2026 ALTA/NSPS Land Title Survey" with a written Table A list.
  • Tell the surveyor the planned use in writing, and arrange access to the property, adjoiners and offsite easements.
  • For a development site, consider items 1, 3, 4, 5, 6(a)/(b) with a zoning report, 11, 13, 14, 16, 17, 18 and 20.
  • Negotiate a design-level topographic survey or wetland flag locations under item 21 if you need them.
  • Check the certification: 2026 standard, the right entity names, the Table A items you ordered.
  • Review the draft: title source, summary of exceptions, blanket easements, encroachments, access, and every note.
  • Send the final plat to the title company and get its position on survey exceptions and endorsements before the objection deadline.

Sources

This guide explains the standard; it is not legal or surveying advice. Your licensed surveyor, title insurer and counsel decide what a specific property needs.